Singlemode and multimode plant engineered against a real loss budget, fusion spliced, and certified to Tier 1 and Tier 2 so the margin is documented instead of assumed.
Fiber either works or it does not, and when it does not, the cause is usually contamination or a splice that was never verified. Roughly the majority of field fiber faults trace back to a dirty or damaged endface — a defect invisible to the naked eye. We inspect every endface under a scope before mating, and we build to a calculated loss budget so there is measurable headroom for future splices and moves.
Link loss calculated from fiber attenuation, splice count, connector count and safety margin, then compared against the optics' power budget before the design is committed.
Core-aligned fusion with splice loss estimated at the machine and verified bidirectionally by OTDR. Mechanical splices only where a permanent repair is not possible.
Direct-buried, duct, aerial and riser construction, with the transition to inside plant handled per code — including the unlisted-cable distance limit at the entrance.
Every connector scoped to the IEC 61300-3-35 pass/fail criteria and cleaned until it passes. No exceptions, including factory-terminated assemblies.
OS2 singlemode for distance and future capacity, OM3/OM4/OM5 multimode where the optics and lengths justify it. Fiber count sized for growth, since the labor to place a cable dwarfs the cost of extra strands.
Route drawing, splice plan, strand assignment and the calculated loss budget the installation will be measured against.
Pulling tension and bend radius controlled, with the minimums respected — macrobend loss is a real and permanent penalty on singlemode.
Splicing in a controlled environment, trays organized and labeled, enclosures sealed and mapped.
Tier 1 insertion loss with an optical loss test set, bidirectional. Tier 2 OTDR traces to characterize every event along the span. Both delivered, with the loss budget shown alongside the measured result.
Code editions are revised periodically and local authorities amend them. The requirements that apply to your project are confirmed against your jurisdiction during design.
No. OTDR characterizes events along the span; it does not measure true end-to-end insertion loss. Tier 1 with a light source and power meter is the acceptance measurement. Tier 2 tells you where a problem is.
A splice between fibers with different backscatter coefficients can read as a gain in one direction. Averaging both directions is the only way to get the real number.
Almost always. The cable is a fraction of the cost of the placement labor, and a dark strand is the cheapest capacity you will ever buy.
Tell us the building, the constraints and the deadline. We will tell you what the work actually involves before anyone quotes a number.